II-6 Case Program Management Policy

II-6  Case Program Management Policy


Overview

Version 0.95 DRAFT
Last Revision Date: April 22, 2008
Approval Date: DRAFT
Approval Authority:  Vice President for Information Technology Services/CIO


Purpose

The purpose of this policy is to establish the standard criteria for the required application of the formal project management methods for information technology (IT) centric projects where ITS resources are involved.

Scope

This policy applies to all work products produced or maintained by Information Technology Services (ITS). 

Cancellation

Not applicable.

Policy Statement
General
The use of the formal project management methods as defined in ITS Procedure II-6a is required for ITS projects that meet the defined criteria. The objective is to ensure that projects are delivered with acceptable schedule, budget, scope and quality.

Criteria

Any project that meets any one of these listed criteria shall employ formal project management
  1. Any project that is estimated to consume more than 80 ITS person-hours of work effort.
  2. Any project that requires cross-departmental within ITS.
  3. Any project that is estimated to consume more than $8000.00 in non-salary costs.

Process
The following standard procedures are provided for the implemnentation of this policy.
II-6a  ITS Project Management Methodology Definition
II-6b  Information Techology Project Classifications
II-6c  ITS Project Initiation Form


Definitions

Project: A temporary endeavor undertaken to create a unique product or service and has a defined beginning and a defined end.

Non-Salary Cost: Project costs not including salary.

Cross-departmental: Engaging more then two or more departments within the Divison of Information Technology Services.

IT Centric Projects:ITS is involved in determining and implementing a product or service.



Responsibility
The ITS Program Management Office (PMO) is responsible for assisting Project Managers in completing all aspects of the Project Management process.
The  ITS Directors are responsible for approval activities in the Project Management process.
The ITS Project Managers are responsible for adherence to this policy.

Consequences

Failure to comply with this policy may result in one or more of the following actions:

  • CIO, Deputy CIO, and PMO Director place the project on “Hold” until compliance has been achieved.
  • CIO, Deputy CIO, and PMO Directors withhold funding or personnel resources for the project until compliance has been achieved.


Policy Review Cycle
This policy will be reviewed every two years on the anniversary of the policy effective date, at a minimum. The policy may be reviewed on a more frequent basis depending on changes of risk exposure.